Auckland Airport Runway Shortened

Auckland Airport's runway is currently shortened by one kilometer. However, the airport is still able to function.

Coronavirus: Air New Zealand refunds little comfort to travellers ...
The airport started working on preparing panels in the touchdown area which had become damaged. An 80-strong construction team is working to shorten the runway.

The repair work on the runway replacing 280 slabs of concrete. It was planned for later this year, but the drop in the air traffic due to Corona virus has allowed the airport to begin the work earlier.